ADOT starts widening 11 miles of I-10 between Loop 202 and Gila River

A palo verde tree beside Interstate 10 in Arizona

PHOENIX — Construction has started on the next phase of the Interstate 10 widening between Phoenix and Casa Grande, covering an 11-mile stretch in both directions between Loop 202 and the Gila River, the Arizona Department of Transportation announced Tuesday, KTAR News reported.

The work is the third of four segments in the 26-mile I-10 Wild Horse Pass Corridor Project, which aims to ease congestion and shorten travel times.

Crews will add a third general-purpose lane in each direction along the 11-mile stretch, plus an HOV lane in each direction between Loop 202 and Riggs Road, according to ADOT.

Work on the first segment, replacing the I-10 bridges over the Gila River, began in May 2024, and finishing touches are scheduled for next month.

The second segment, under construction since January 2026, covers 10 miles from Gas Line Road to just north of Casa Grande. Crews there are adding a third lane each way, rebuilding the Pinal Avenue interchange and building a new interchange at Seed Farm Road.

All four segments are expected to be finished by late 2029.

Sources: KTAR News. Thee Arizona Times uses AI-assisted reporting reviewed against the sources listed.